• Construction was nearly complete in 2020. <br /> • The Contractor installed the four (4) parking lot light poles. Each was to <br /> include a banner. Only two (2) include a banner. In early Jan 2022, two (2) <br /> replacement light poles were delivered to the site. The Contractor is <br /> pushing the Electrical subcontractor to install the two (2) replacement light <br /> poles within the next two weeks. <br /> • KC continues to push the Contractor to resolve the light pole issue and <br /> provide the paperwork required to close out this project with the Village. <br /> • KC efforts are nearly complete pending project closeout. <br /> • Village / Bain Park Survey and Masterplan (KC 12-0072) <br /> • Work remains underway in preparation for 2022 construction. <br /> • Village / Local Watershed Revitalization Prosect (LWRP) / Nine Element Plan <br /> (KC 4077-001 ) <br /> • On April 26, 2017, the Village Board authorized this project. <br /> • KC scope resulted in the development of a Wappinger Creek Watershed <br /> Characterization and Recommendations Report, which has been <br /> contributed to by the Village and the Wappinger Creek Watershed <br /> Intermunicipal Council (WIC). KC provided the latest draft report and <br /> recommendations in Dec 2020 for review. <br /> • At the July 23, 2021 WIC Council Meeting, it was agreed that review and <br /> then subsequent editing of the report and recommendations is nearly <br /> complete. <br /> • No additional comments have been received. <br /> • This winter 2022, KC will finalize the last edit of the Watershed <br /> Characterization and Recommendations Report. <br /> • After completion of the last edit of the report, the Village is to host one more <br /> Public Meeting. That will conclude KC's work for this project. <br /> Village / Route 9 Sewer 2022 (KC 12-0180) <br /> • As requested, KC has provided an updated proposal for this project. <br /> • KC requests that the Village Board please review and respond to KC <br /> proposal letter dated Jan 26, 2022 for Route 9 Sewer 2022. <br /> Approval KC requests that the Village Board please review and respond to KC proposal <br /> letter dated Jan 26, 2022 for Route 9 Sewer 2022. <br /> Cost <br /> Page 2 of 6 <br />